Future of Flooding | Hexham Flood Alleviation Scheme
Raising standards
Low carbon concrete mixes being trialled on a flood alleviation scheme in Northumberland could be a key environmental solution for future projects. Sotiris Kanaris reports.
Heavy rainfall during Storm Desmond in December 2015 made the River Tyne overtop its banks north of Hexham town centre in Northumberland. The Bridge End and Tyne Mills Industrial Estates – which are on opposite sides of the river – were flooded, with 90 properties including businesses, local services and three houses impacted. There were no flood defences to protect them.
It was decided that, as the industrial estates are important contributors to the local economy, it was essential that flood defences be built to protect them in the future. This led to the £6.5M Hexham Flood Alleviation Scheme, which has just been completed.
The legacy could be much broader than just the protection of Hexham, as the Environment Agency worked with contractor Bam Nuttall and designer Arup to trial low carbon concrete mixes for the scheme.
Infrastructure project clients will be looking at this scheme when choosing their concrete mixes for permanent works in the future as the trial involves testing mixes in permanent works for the first time.
According to the project team, these concrete mixes developed by Tarmac contain only a small share of the carbon dioxide equivalent found in CEM 1 Ordinary Portland Cement.
Neither are currently covered by British Standards.
BOOSTING PROTECTION
Modelling conducted by the Environment Agency after the 2015 flood showed that the Tyne Mills Industrial estate on the south bank of the Tyne had a 2% chance of flooding in any given year. The Bridge End Industrial Estate on the north bank had a 1.33% chance of flooding.
The flood alleviation scheme involves the construction of flood defences to reduce that figure to 1% for both industrial estates.
Reinforced concrete flood walls with heights ranging from 1m to 1.5m were identified as the primary solution. The design included a 195m long flood wall to improve flood protection for the Tyne Mills Industrial Estate and a 245m long flood wall for the Bridge End Industrial Estate.
Environment Agency project executive Vanessa Collins says the initial design included an additional 100m of flood wall to protect the Tyne Mills Industrial Estate from a small watercourse called the Skinnersburn. When River Tyne’s water level rises, water backs up in the Skinnersburn, which then floods into the estate.
She explains that just before the full business case was finalised, a decision was taken to realign the flood walls and create a flood control structure, removing the need for this additional stretch of flood wall.
Bam Nuttall design manager Kevin Bulman describes the flood control structure as “essentially a culvert with a headwall on either end” with a tidal flap on the downstream end of the culvert.
KEY FACT
£6.5MCost of Hexham Flood Alleviation Scheme
He adds: “On a normal flow, the water coming down Skinnersburn will pass through the tidal flap. On a flood event when the water comes [from the Tyne] up Skinnersburn it will push the tidal flap closed and the water just cannot go further upstream than this point.”
Collins identifies the removal of this section of flood wall as one of the key contributors to the final 49% reduction in the scheme’s whole life carbon from early design phases to 544kg CO2e.
The flood protection solution for the Bridge End Industrial Estate involved building a 245m reinforced concrete flood wall and raising a 125m embankment by up to 400mm.
“The best solution was for the Environment Agency to purchase that land and demolish the buildingEarly on in the scheme, it became apparent that the construction team would have faced space limitations at the western end of the southern riverbank where flood walls had to be constructed. The structures had to be installed between a revetment and the “Reiver Sports” building which housed a Northern Powergrid substation.
“During feasibility it became clear that the best solution was for the Environment Agency to purchase that land and demolish the building, which made it safer and easier to build the scheme,” says Collins.
The substation was relocated into a dedicated building approximately 30m from its original position within the same plot of land.
Collins adds that it is unusual for the Environment Agency to buy land, as it is usually maintaining assets on property owned by others.
All main construction works on the flood walls, embankments and flood control structure were completed in spring this year. The main construction contract was completed this summer, so the focus of works on site has now shifted to habitat restoration and landscaping.
TESTING CONCRETE
Flood wall construction may have been completed, but the Environment Agency, Bam Nuttall, Arup and Tarmac are still carrying out tests on a 27m long section used for the low carbon concrete trial.
Funding of £88,000 from the Environment Agency’s net zero carbon innovation pathway pilot fund was granted for this trial and was not part of the funding for the overall project.
Funding for the rest of the project came from a number of other sources: £1.7M from the government as economic recovery funding after the Covid-19 pandemic, £300,000 from the Northumberland regional flood and coastal committee plus £200,000 from Northumberland County Council. The rest was grant in aid from the government.
One of the new Tarmac mixes being used is Portland Limestone Ternary cement. The cementitious elements comprise 35% CEM I – which is 100% Ordinary Portland Cement – 20% limestone filler and 45% ground granulated blast furnace slag (GGBS). This mix’s carbon dioxide equivalent is 119kg/m3 3, 64% lower than standard CEM I.
The other concrete mix being tested uses an alkali-activated cementitious material (AACM) comprising 95% GGBS and 5% CEM I. This mix has 100kg/m3 CO2e, 70% less than the standard CEM I concrete.